Investment components
reform components
-
PC-I Approved in PDWP
29th May 2015 -
Loan Negotiation held at ADB Pakistan Resident Mission Islamabad
3rd Sep 2015 -
Advance procurement request sent to ADB
8th Sep 2015 -
ADB approved the advance procurement request
15th Sep 2015 -
Loan Negotiation approved by ADB
12th Oct 2015 -
ECNEC cleared the project
14th Nov 2015 -
Administrative Approval issued
9th Feb 2016 -
Loan Agreement signed
30th Aug 2016 -
Loan Effective Date
5th Oct 2016 -
Notice To Proceed issued to Project Management Consultants
14th Nov 2016 -
Commencement Letter of 6 Civil Works issued
2nd Dec 2016 -
Commencement Letter of 3 additional Civil Works issued
28th Jun 2019 -
Original Loan closing date
30th Jun 2020 -
Extended Loan closing date
30th Jun 2020