Investment components
reform components
PROGRESS OF CIVIL WORKS (6+3=9, 328KM + 80 KM = 408KM)
Road No. | Name of Road | Length in KM | Name of Firm | Completion Cost | Target Achieved |
---|---|---|---|---|---|
P-1 | Thull to Kandhkot | 44 | M/S Metallurgical Corporation Of China Ltd. – M/S Umer Jan Co [Jv] | 1,700.450 | All Works Completed Taken over Certificates issued. |
P-2 | Sheranpur to Ratodero | 36 | M/s Xi'an Industrial Development Co. Ltd of China Road & Bridge Corporation-
M/s Sardar M. Ashraf D. Balouch [JV] |
1,326.058 | |
P-3 | Khyber to Sanghar via Tando Adam | 64 | M/s Xinjing Beixin Road & Bridge Group Co. Ltd. | 2,503.883 | |
P-4 | Sanghar to Mirpur Khas via Sindhri | 63 | M/s Xinjing Beixin Road & Bridge Group Co. Ltd. | 2,267.973 | |
P-5 | Tando Mohammad Khan to Badin | 67 | M/s Xi'an Industrial Development Co. Ltd of China Road & Bridge Corporation -
M/s Sardar M. Ashraf D. Balouch [JV] |
3,299.414 | |
P-6 | Digri to Naukot | 54 | M/s Xinjing Beixin Road & Bridge Group Co. Ltd. | 3,066.427 | |
P-7 (i) |
Tando Allahyar to Chamber | 19 | M/s Umer Jan & Co – M/s Noor-ul-Haq & Brother (JV) | 624.897 | |
P-7 (ii) |
Sehwan (N-55) to Dadu via Talti, upto Dadu-Moro road | 32 | M/s JSHT – M/s NCC – M/s SB (JV) | 1,083.360 | |
P-7 (iii) |
Jehan Khan (N-65) to Faizu Laro (N-55) via Chak | 29 | M/s Umer Jan & Co. | 1,115.785 | |
TOTAL | 408.00 | 16,988.20 |